The Township has started the above subject paving program. Below is in alphabetical order a list of the streets included in the program, and the approximate dates major work efforts will be performed. The roads will typically remain open to local traffic during milling and other preparatory work. However, during the paving operation the roads will be closed to all traffic and are typically re-opened by 6:00 p.m. on the day it is paved.
The schedule below is dependent on good weather, and no equipment breakdowns. Unfortunately, this type of work is susceptible to the weather, unexpected equipment failures, and unforeseen site conditions. Please check back from time to time as the schedule will be updated periodically to account for these unpredicted circumstances, and as the project progresses.
STREET NAME | MILLING | PAVING |
AMSTRONG AVENUE | 10/10/23 | 10/11/23 |
AMY WAY | 10/10/23 | 10/11/23 |
BOONSTRA DRIVE | Complete | Complete |
CANTON ROAD | Complete | Complete |
CHOPIN DRIVE | Complete | Complete |
COLVILLE ROAD | Complete | Complete |
DEERFIELD ROAD | Complete | Complete |
DIANE COURT | Complete | Complete |
DORSA AVENUE | Complete | Complete |
FERRARA AVE | 10/11/23 | 10/11/23 |
FREDERICK COURT | Complete | Complete |
LEDGE ROAD | Complete | Complete |
LESLIE DRIVE | Complete | Complete |
LINDEN LANE | 10/10/23 | 10/11/23 |
MILLER ROAD | Complete | Complete |
NAVAJO AVENUE | 10/11/23 | 10/11/23 |
NOTTINGHAM ROAD | Complete | Complete |
OXBOW PLACE | Complete | Complete |
PANCAKE HOLLOW DRIVE | Complete | Complete |
SQUIRE LANE | Complete | Complete |
VERKADE DRIVE | Complete | Complete |
WHITTAKER COURT | Complete | Complete |
YORKTOWN ROAD | Complete | Complete |