The Townships Municipal Aid Program for the resurfacing of Nellis Drive (entire length) has begun. Below are the approximate dates for when major work efforts will be performed. The road will be closed to traffic during the milling and paving operations, typically re-opening by 6:00 pm
The schedule below is dependent on good weather, and no equipment breakdowns. Unfortunately, this type of work is susceptible to the weather, unexpected equipment failures, and unforeseen site conditions. Please check back from time to time as the schedule will be updated periodically to account for this unexpected circumstances, and as the project progresses.
| Inlet Reconstruction and Concrete Work | Milling and Paving |
| 8/10/2023 to 8/18/2023 | 8/21, 8/22 & 8/23 |